Ho Chi Minh City’s Ring Road No. 3 Construction Project.

A. Brief contents of the investment report:

 

1.      General:

The Ho Chi Minh City’s Ring Road No. 3 is one out of four important ring roads in the Vietnam’s expressway network development plan up to 2020 and the vision after 2020, which was approved by the Prime Minister in Decision No. 1734/QD-TTg dated December 1, 2008

1.      Investment objectives:

-       Long-term objective: Socio-economic development of Ho Chi Minh City and of provinces in the Eastern region of Southern Vietnam; especially in the Southern key economic area.

-       Short-term objective: Project preparation for achieving the objective consisting in putting the project into the construction stage, meeting the demand for transportation of goods of provinces in the Mekong Delta to Nhon Trach industrial zone and Cai Mep - Thi Vai deep waters port, minimizing traffic jam in Ho Chi Minh City area.

2.      Contents and scale of investment:

3.1 Contents:

a) Alignment:

-       Start point: This point intersects with the Southern inter-regional expressway in NhonTrachCity, Dong Nai province.

-       End point:  The end point of the Ring Road 3 is selected as two following  opitions:

+     The option 1: Connecting to Cho Dem intersection under Binh Chanh District – Ho Chi Minh City (The revision opition).

+     The option 2: Intersecting with Ho Chi Minh City – Trung Luong Expressway at the location that is far from Cho Dem intersection 2,9Km in the South. This is the start point of the inter-provincial road in the South.(The old option).

b) The route passes through the following basic control points:

          Nhon Trach City ® Nhon Trach bridge (crossing Dong Nai river) ® Tan Van three-way crossroads (National Highway (NH.) No. 1A) ® Intersection at Hoa An bridge end (NH. No. 1K) ® Thu Dau Mot town (NH. No. 13) ® Binh Goi bridge (crossing Saigon river) ® Tan Hiep industrial zone (NH. No. 22) ® parallel to An Ha canal ® My Yen - Tan Buu industrial zone ® The end point (as the above mentioned options).

Note:

-       The alignment remains unchanged and is the same as the alignment which was approved by the Prime Minister in the following Decisions:

+        Decision No. 101/QD-TTg dated January 22, 2007 concerning the transport planning of Ho Chi Minh City;

+        Decision No. 1734/QD-TTg dated December 1, 2008 concerning the approval of Vietnam’s expressway network up to 2020 and the vision after 2020;

+        Decision No. 24/QD-TTg dated January 6, 2010 concerning the adjustment of the construction planning of Ho Chi Minh City up to 2025.

-       The section from Tan Van ® My Phuoc: The alignment follows proposals of Binh Duong People Committee at the letter No. 914/UBND-KTN dated 07/4/2010.

-       End point: as two above mentioned options.

c) Total length: 89,3 Km.

3.2 Investment scale:

-       Urban expressway , design speed in range of  80-100km/h.

-       Cross-section size: 68.5m in width (including 7m sidewalk on each side), of which:

+       For the urban expressway: 6 lanes for motorized vehicles (3.75m) + 2 emergency stop lanes (3.00m).

+       For parallel roads: 2 mixed vehicles lanes (3.5m) for each side.

-       Right of way: 100m -120m in width.

3.      Construction location: The alignment through the area of three (3) provinces and cities, namely Ho Chi Minh City (54,3Km), Dong Nai province (11,6Km), Binh Duong province (23,4Km).

4.      Total investment estimated cost:

        The total preliminary estimated cost (based on prices in quarter II/2010) is VND  34,927 billions and is listed in the following table:

No.

Cost item

Estimated investment (billion VND)

Section 1 (26,3 Km)

Section 2A

(16,3 Km)

Section 2B

(17,5 Km)

Đoạn 3

(29,2 Km)

Sub- total (89,3Km)

1

Construction costs

9.243

1.074

6.150

10.262

26.729

2

Project management,  Investment consultancy, Other costs

1.386

161

923

1.539

4.009

3

Compensation for land acquisition costs

332

92

221

420

1.014

4

Contingencies

1.096

133

729

1.222

3.175

 

Total

12.058

1.459

8.023

13.444

34.927

Note:

-       Section 1: From the start point (Southern inter-regional expressway in Nhon Trach city) to Tan Van intersection.

-       Section 2A: From Tan Van to Binh Chuan District (salvaging My Phuoc – Tan Van expressway in the phase 1. In the phase 2, it will be extended according to the master plan of the Ring Road 3).

-       Section 2B: From Binh Chuan district intersection to NH. No. 22 intersection.

-       Section 3: From NH. No. 22 intersection to the end point (Ho Chi Minh City-Trung Luong expressway).

5.      Investment budget: Intention is to mobilize various sources of capital in a flexibleinvestment form: BOT, PPP, BT, ODA loans, state budget.

6.      Project implementation period: 2010 – 2016.

B. Implementation process:

-       The pre-feasibility study report was considered and reviewed by the MOT at a meeting held on March 11, 2010, and based on the conclusion of the MOT’s leader, the project scale complies with the Prime Minister’s Decision No. 1734/QD-TTg.

-       At present, TEDIS is urgently finalizing the pre-feasibility study report based on appraisal opinions.

C. Recommendation:

    Based on the Consultant’s study results and the economic development situation of the area together with the requirement for development of transportation infrastructure, it is recommended as follows:

1.     The component project "benchmarks setting out for Land acquisition and right-of-way ” should to be implemented immediately for managing and keeping land for construction of the project. 

-       Source of capital: The State’s budgetary capital.

-       Implementation progress schedule: 2010 – 2011.

2.     The Ring Road No. 3 investment project should be divided into component projects in the following priority order:

-       Priority 1 : Tan Van→ Nhon Trach section (26.3km)

-       Priority 2 : Tan Van→ NH. No. 22 intersection section(Section 2A, Section 2B, total length 33.8km)

-       Priority 3: NH. No. 22 intersection→ intersection with Ho Chi Minh City - Trung Luongexpressway section(29.2km).

3.     Early investment in Tan Van - Nhon Trach component project according to the following contents:

3.1 Division of investment into phases:

-       Division of investment into two (2) phases. Phase 1: Investment for construction of 4 lanes; land acquisition and landmark benchmarks setting out based on the final phase scale; Acquisition of land within land acquisition demarcation benchmarks.

-       Addition of a section connecting Thu Duc intersection to Ring Road No. 3 (Tan Van – Nhon Trach section with a length of about 4.0 km), total length of the component project: About 30.3 km.

-       The Employer: The MOT.

-       Total investment of phase 1 : About VND 7,000 billions (USD 372 millions) .

+ Civil works                                          : 256 million USD

+ Consultant, Management, other cost     :  55 million USD

+ Land acquisition                                    :  24 million USD

+ Contingency                                        :  37 million USD

-       Source of capital:

+   Land acquisition cost: Mobilization of local government capital for immediate implementation.

+   Construction cost: ODA capital and mobilization of other sources of capital in PPP and BOT forms.

3.2 Implementation period : 2010 - 2013.

P. KTKT
Send by Email Print Back

CÁC TIN KHÁC
Vi Thanh - Bac Lieu Project  (6/12/2010)
The Connector Road from the East-West Avenue project to the Ho Chi Minh –Trung Luong Expressway project  (6/12/2010)
My Thuan - Can Tho Expressway Project  (6/12/2010)
Ben Luc – Hiep Phuoc component project (Belonging to the Ho Chi Minh City Ring Road Project No.4)  (6/12/2010)
Tan Van – Nhon Trach Component Project under the Ho Chi Minh City Ring Road Project No.3  (6/12/2010)